This proposal will suggest adding an OR clause to queries that gather the contract to patient mapping in order to improve efficiency on both the client and server.

Status

  • Status: Rejected (This RFC was previously approved but after further discussion within the BFD team it has been retroactively rejected because the parameter passing is inappropriate. If this functionality is still required a new approach should be discussed and the RFC updated and re-reviewed.)
  • Implementation JIRA Ticket(s):
    • N/A

Table of Contents

Motivation

AB2D has long running export jobs where the amount of time the job takes is critical for customer happiness. In order to lessen the amount of time a job takes to run, we will need to be able to improve performance in every section of our code. One part that takes a long time is the call to the Patient URL that maps contracts to beneficiaries on a monthly basis. Being able to query multiple months in the same call will reduce the load on the BFD database since it will reduce the number of calls needed to it, and be more efficient since we will reduce the number of API calls we need to make. It is more efficient on the server side to make 1 call to get the data, than it is to make 6 different calls that gather the same amount of data.

Proposed Solution

The solution will allow a client to specify any number of months that they want to be passed to the BFD server. The BFD server will be able to parse what months the client is asking for, and then return all of the months at once, instead of having the client make individual requests.

Proposed Solution: Detailed Design

PatientResourceProvider.queryBeneficiaryIds currently takes in just one field, and one value. This code should be changed so that it takes in a list of objects. The new object would just be a simple value class that can hold a field and value

PatientResourceProvider.queryBeneficiaryIds can take in an object like so: // Assume getters and setters class FieldValue { private String field; private String value; }

https://bluebutton.cms.gov/resources/variables/ptdcntrct01 is the current variable for how data is sent over from AB2D for the month of Jan. to the BFD server

When it is used with an identifier, it is combined with a contract, e.g. https://bluebutton.cms.gov/resources/variables/ptdcntrct01|Z0001

In order to send over multiple months using the FHIR client libraries, the systemAndIdentifier method takes 2 strings, the first being the one we're interested in (the system). Months can be separated by a delimiter, so that multiple months can be included, e.g. https://bluebutton.cms.gov/resources/variables/ptdcntrct01-02-03

This value can be parsed by BFD to determine if there should be an or parameter in the event there's a list of items sent over. One month would mean that there's no need for a month parameter. The SQL query in queryBeneficiaryIds can provide an OR clause when necessary.

Proposed Solution: Unresolved Questions

Before a solution goes into place, how can we validate that this actually does help performance? Performance testing this with real world examples, e.g. comparing AB2D performance querying 6 months separately vs. 1 query with 6 months.

Will other groups use this solution?

Proposed Solution: Drawbacks

This may not work if it becomes a pain to parse apart multiple months, but it shouldn't be much of an issue, since there will be a large gain from being able to query for multiple months at once, instead of doing them one at a time. If clients abuse this and query more months than what they need, that would be an issue, but any client could abuse an API.

Proposed Solution: Notable Alternatives

We have to make a design fit within the FHIR spec, so unfortunately there's not too much room for alternatives. This solution tries to make as few changes as possible to the code on BFD's side so that it's a simple one that can utilize the existing system for using a month parameter, and simply expand it to optionally use additional months.

Future Possibilities